Compulsory Land Acquisitionfor Road Infrastructure Projects in Uganda

A Practitioner's Mind · by William Matovu

A step-by-step guide to acquiring land for Uganda's roads fairly, on time and at lower cost, from the man who led land acquisition at the Uganda National Roads Authority.

149 national road projects≈ 400,000 affected people15+ years in the field
Book cover: Compulsory Land Acquisition for Road Infrastructure Projects in Uganda, A Practitioner's Mind, by William Matovu, 1st Edition
About the book

Roads start on someone's land

Too many road projects in Uganda begin before the land is ready. This book follows a project from first planning to the year after the road opens, and shows where land acquisition goes wrong and how to get it right.

For government

Ministries, departments and authorities

A phased process that has land ready before contractors arrive, saving time and public money.

For practitioners

Surveyors, valuers, lawyers, sociologists

The working detail: strip maps, gazetting, valuation, disclosure, titling and records.

For communities

Families whose land is affected

What the law entitles you to, what happens at each stage, and how to protect your household.

Key questions

Building roads while protecting landowners

Every road project has to balance public need with private rights. These are seven of the questions the book works through, with lessons from Uganda's own reforms and from its neighbours.

Chapter 1 · Chapter 8

When should compensation be paid: before or after the land is taken?

Uganda's Constitution requires prompt, fair and adequate compensation before government takes possession, a strong protection for owners.

Kenya and Tanzania allow possession first, with interest paid until compensation is settled. The book compares the two approaches and asks what Uganda could adapt to deliver roads sooner while keeping owners protected.

Chapters 3–5

How do you earn a community's trust?

Early meetings, elected grievance committees and clear disclosure turn affected families into partners in the project rather than opponents of it.

Engage before the first survey peg.
Chapter 1 · 8

How can valuations be agreed sooner?

Clear national valuation standards and a firm legal footing for the valuer's office would reduce disputes. The proposed Valuation Bill points the way.

A reform already under way.
Chapter 1

How should compensation be shared on kibanja land?

Kibanja holders and registered owners often share compensation by common practice. The book makes the case for clear, written rules everyone can rely on.

Clarity helps owners and agencies alike.
Chapter 4

What happens after a corridor is gazetted?

Gazetting sets a cut-off date and pauses new developments. The book explains how to match it to funding and timelines so families aren't left waiting.

Plan the money with the map.
Chapter 8

Why a dedicated budget for land works

Since FY 2018/19, land acquisition at UNRA has had its own budget line. The result: faster payments, fewer contractor claims and fewer court cases.

A reform that paid off.
Chapter 5

How can families get the papers they need?

Letters of administration and powers of attorney can delay a payment. The book sets out how project teams can help, especially vulnerable households.

Support reaches more rightful owners.

The full discussion, with cases and recommendations, is in the book.

Get the book
From the record

What good planning delivers

When UNRA brought land acquisition in-house in 2015 and planned it alongside design, a study of 45 road projects found clear gains.

64.5%

Lower cost of acquiring land for road projects

53.2%

Less time to complete land acquisition

UGX 32.5bn

Saved over the study period, about UGX 3.8bn a year

10–15%

Share of road construction cost the compensation fund should fall within, in the author's experience

For affected families

A road is coming through your land. What now?

The five moments that matter most to a household, in the order they happen.

  1. Go to the meetings

    Before any survey, the project meets the community. A grievance committee is elected from your village to carry complaints.

  2. Stop building at the cut-off

    Once the corridor is gazetted, new buildings or crops are not eligible for compensation.

  3. Check the strip map

    It's displayed publicly. Confirm your name and plot boundaries before the valuation is final.

  4. Have your papers ready

    Title, sale agreement, letters of administration. Missing documents are a top cause of delay.

  5. Plan the money first

    A 15% disturbance allowance is added, or 30% with under six months' notice. Replace land, house and income first.

General information from the book, not legal advice.

Inside the book

Eight chapters, in the order a project runs

From the first planning decision to the year after the road opens, with a comparison of Ethiopia, Kenya and Tanzania.

  1. 01

    Introduction

    Land tenure, the law, key concepts and what slows acquisition down.

  2. 02

    Investment Planning

    Screening social risk before money is committed.

  3. 03

    Preliminary Design

    Options, the RAP framework and stakeholder engagement.

  4. 04

    RAP Preparation

    Surveys, valuation, census, gazetting and vulnerable households.

  5. 05

    RAP Implementation

    Disclosure, financial literacy, payment, titling and clearing the land.

  6. 06

    During and Post Construction

    Design changes, injurious affection and the completion audit.

  7. 07

    Information Management

    Keeping thousands of land titles and files safe and findable.

  8. 08

    Last Thoughts

    Lessons from three neighbours and from UNRA's reforms.

Endorsements

The first of its kind in Uganda

It has a great wealth of information. It is the first of its kind in the country.Pheona Wall NabaasaPresident, Uganda Law Society, at publication
A good contribution to the solving of the prevailing land acquisition problems.Eng. Samuel MuhooziDirector, Roads and Bridges Development, UNRA
A good reference point for anyone in this business or affected by the actions of acquisition of land for public use.Eng. Charles KizitoHead, Corporate Strategy, UNRA
William Matovu
The author

William Matovu

A land surveyor and land acquisition, resettlement and social sustainability specialist. He was Head of Land Acquisition at the Uganda National Roads Authority for five years until December 2020, and earlier headed land surveying during the transformation of Kampala City Council into KCCA.

He is a fellow of the Institute of Surveyors of Uganda, holds a BSc in Land Surveying and an MSc in Management, and trains trainers in financial literacy.

Years in land management
15+
National road projects
149
Households reached
75,000+
Project affected persons
≈ 400,000
Get the book

Join the debate with the full story

On Kindle worldwide through Amazon, and in print in Uganda through Aristoc Booklex.

Worldwide

Amazon

Kindle ebook, USD 9.99, or free to read with Kindle Unlimited. Opens the Amazon store for your country.

Buy on Amazon
In Uganda

Aristoc Booklex

Buy the print edition from Uganda's leading bookshop, online or in store.

Buy at Aristoc

Bulk orders for agencies, firms, universities and law schools:

business@rendsmedia.com
+256 705 283 188
Order on WhatsApp
ISBN 978-9913-637-52-7 (print)First EditionRends Digital Production